 PORDENONE. A single, maxiappalto for the construction of the hospital, the central technology and the citadel of health: it announced yesterday the general manager of Aas 5 Paul Bordon to the Conference of Mayors for the presentation of the Plan implementing local (Pal).


 


 A game by 171 million euro, one procurement heavier than the province of Pordenone memories. All while yesterday came even by the municipality, for permission to build the new hospital.


 


  The call . “We have decided that there is a unique competition to build the new hospital – he said – the citadel of health and technological station. A procedure alone to manage in an integrated construction of these three works “.


 


 Bordon explained that these days have come to the ACD 5 opinions requested by the evaluation team of the Region, firefighters and prevention department of the same Aas 5. Yesterday came also permission to build the new hospital from town of Pordenone.

 


 “It will be a race of enormous size – continued Bordon – and take away months of work for this procedural process. We count, between June and July, reaching the award to the pool of companies which will have to proceed to the final design and construction. We hope that next year, at this time, there was the delivery of the work. “


 


 For now, the schedule announced in recent months has observed: “We are pleased – said Bordon – that the process that we announced here a year ago has been fully respected, even a few days earlier than planned to arrive approval of the notice. “

 


 The document will be ready in a few days to be approved later this year.


 


  Works . The start of construction of the new hospital will be the construction of the new morgue whose work, entrusted, will begin in March.


 


 Then, in a year or so, it will start with the construction of the hospital itself. The Director General also explained that the first phase of work will involve the construction of the underground car park set to take Montereale. Then he will go to the hospital itself.


 


  Money . There are many, for one of the largest contracts that the province memories. To work alone is expected to cost 132 million Euros, in addition to VAT and other charges that carry the value of 171 million Euros.


 


 Of these, 150 million are planned for the hospital, 12 to the citadel of health and 9 for the technological station. The race will be European.


 


  projects. The opportunity to update the first citizens on the state of the art for the new hospital was drawing to the mayors of the local implementation plan (Pal) for 2016.


 


 At the heart of the health planning document for next year with something new: the money will be provided since the beginning of year for greater certainty. For 2015, the company is poised to approve a balanced budget.


 


  The reorganization . It also decided the timing of the transfer of functions between Cro Aas and 5 as required by health reform. By June 2016 it is expected to transfer the function of pathology from Cro AAS 5, oncology

ACD 5 to Cro, cardiology from Cro AAS 5.
 


 Nuclear medicine hospital of Pordenone to Cro will be transferred by December 2016, and the functions of the laboratory analysis, microbiology and virology from Cro AAS 5 by October.


 